BUSN Math..Problem

BUSN Math..Problem

Problem 11-5

 

Manager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must develop an aggregate plan given the forecast for engine demand shown in the table. The department has a normal capacity of 130 engines per month. Normal output has a cost of $60 per engine. The beginning inventory is zero engines. Overtime has a cost of $90 per engine.

 

 

  Month  
  1 2 3 4 5 6 7 8 Total
  Forecast 120 135 140 120 125 125 140 135 1,040
 

 

a. Develop a chase plan that matches the forecast and compute the total cost of your plan. (Negative amounts should be indicated by a minus sign. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.)

 

  Period                1                2                3                4                5                6                7                8             Total
  Forecast 120 135 140 120 125 125 140 135 1,040
  Output                  
    Regular                  
    Overtime                  
    Subcontract                  
  Output – Forecast                  
  Inventory                  
    Beginning                  
    Ending                  
    Average                  
  Backlog                  
                   
  Costs:                  
  Output                  
    Regular $               $
    Overtime                  
    Subcontract                  
  Inventory                  
  Backorder                  
                   
  Total $               $
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

b. Compare the costs to a level plan that uses inventory to absorb fluctuations. Inventory carrying cost is $2 per engine per month. Backlog cost is $90 per engine per month. (Negative amounts should be indicated by a minus sign. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.)

 

  Period                1                2                3                4                5                6                7                8             Total
  Forecast 120 135 140 120 125 125 140 135 1,040
  Output                  
    Regular                  
    Overtime                  
    Subcontract                  
  Output – Forecast                  
  Inventory                  
    Beginning                  
    Ending                  
    Average                  
  Backlog                  
                   
  Costs:                  
  Output                  
    Regular $               $
    Overtime                  
    Subcontract                  
  Inventory                  
  Backorder                  
                   
  Total $               $
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Problem 11-6

 

Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a normal capacity of 275(00) bolts per month, except for the seventh month, when capacity will be 250(00) bolts. Normal output has a cost of $40 per hundred bolts. Workers can be assigned to other jobs if production is less than normal. The beginning inventory is zero bolts.

 

 

Month 1 2 3 4 5 6 7 Total
  Forecast 250 300 250 300 280 275 270 1,925
 

 

a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Overtime is $60 per hundred bolts. (Negative amounts should be indicated by a minus sign. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.)

 

  Period              1              2              3              4              5              6              7                   Total
  Forecast 250 300 250 300 280 275 270 1,925
  Output                
    Regular                
    Overtime                
    Subcontract                
  Output – Forecast                
  Inventory                
    Beginning                
    Ending                
    Average                
  Backlog                
                 
  Costs:                
  Output                
    Regular $             $
    Overtime                
    Subcontract                
  Inventory                
  Backorder                
                 
  Total $             $
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

b. Would the total cost be less with regular production with no overtime, but using a subcontractor to handle the excess above normal capacity at a cost of $50 per hundred bolts? Backlogs are not allowed. The inventory carrying cost is $2 per hundred bolts. (Round your Average values to 1 decimal place. Negative amounts should be indicated by a minus sign. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.)

 

  Period              1              2              3              4              5              6              7                   Total
  Forecast 250 300 250 300 280 275 270 1,925
  Output                
    Regular                
    Overtime                
    Subcontract                
  Output – Forecast                
  Inventory                
    Beginning                
    Ending                
    Average                
  Backlog                
                 
  Costs:                
    Regular $             $
    Overtime                
    Subcontract                
  Inventory                
  Backorder                
                 
  Total $             $
   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Hints

References

eBook & Resources

Problem 11-9

 

Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to prepare an aggregate plan for the next six months using the following information:

 

 

  MONTH
  1 2 3 4 5 6
  Demand 160 150 160 180 170 140
  Capacity            
     Regular 150 150 150 150 160 160
     Overtime 10 10 0 10 10 10
 

 

Cost Per Unit
  Regular time $50
  Overtime 75
  Subcontract 80
  Inventory, per period 4
 

 

Subcontracting can handle a maximum of 10 units per month. Beginning inventory is zero. Develop a plan that minimizes total cost. No back orders are allowed. (Negative amounts should be indicated by a minus sign. Leave no cells blank – be certain to enter “0” wherever required. Omit the “$” sign in your response.)

 

  Period             1          2         3        4        5       6        Total
  Forecast 160 150 160 180 170 140 960
  Output              
    Regular 150 150 150 150 160 160 920
    Overtime 10 10 0 10 10 10 50
    Subcontract              
  Output- Forecast              
  Inventory              
    Beginning              
    Ending              
    Average              
  Backlog              
               
  Costs:              
    Regular $           $
    Overtime              
    Subcontract              
  Inventory              
  Backlog              
               
  Total $           $
               

Problem 11-14

 

Refer to Example 3 in the textbook. Given the following information set up the problem in a transportation table and solve for the minimum-cost plan: (Omit the “$” sign in your response.)

 

 

  PERIOD
  1 2 3
  Demand   550 700 750
  Capacity        
    Regular   500 500 500
    Overtime   50 50 50
    Subcontract   120 120 100
  Beginning inventory   100    
  Costs        
    Regular time $ 60 per unit
    Overtime $ 80 per unit
    Subcontract $ 90 per unit
    Inventory carrying cost $ 1 per unit per month
    Back-order cost $ 3 per unit per month
 

 

  Minimum total cost $

rev: 04_13_2015_QC

Problem 11-19

 

Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to “schedule production when the projected on-hand inventory would be less than 10 without production.” Suppose that a production lot size of 70 pumps is used. (Leave no cells blank – be certain to enter “0” wherever required.)

 

 

  June   July
  64          1            2            3          4            5          6          7            8
  Forecast 30 30 30 30   40 40 40 40
  Customer orders (committed) 33 20 10 4   2      
  Projected on-hand inventory                  
  MPS                  
  ATP                  
 

 

http://www.viddler.com/embed/b8b1e5f8#

http://www.viddler.com/embed/535773d5#

http://www.viddler.com/embed/124b3553#

http://www.viddler.com/embed/57ef9ae6#

Problem 13-9

 

The Friendly Sausage Factory (FSF) can produce hot dogs at a rate of 5,000 per day. FSF supplies hot dogs to local restaurants at a steady rate of 250 per day. The cost to prepare the equipment for producing hot dogs is $66. Annual holding costs are 45 cents per hot dog. The factory operates 292 days a year.

 

 

a. Find the optimal run size. (Do not round intermediate calculations. Round your answer to the nearest whole number.)

 

  Optimal run size  

 

b. Find the number of runs per year. (Round your answer to the nearest whole number.)

 

  Number of runs  

 

c. Find the length (in days) of a run. (Round your answer to the nearest whole number.)

 

  Run length (in days)  

 

Problem 13-13

 

A mail-order house uses 17,280 boxes a year. Carrying costs are 60 cents per box a year, and ordering costs are $96. The following price schedule applies.

 

 

Number of Boxes Price per Box
1,000 to 1,999 $1.25
2,000 to 4,999 1.20
5,000 to 9,999 1.15
10,000 or more 1.10
 

 

a. Determine the optimal order quantity. (Round your answer to the nearest whole number.)

 

  Optimal order quantity boxes

 

b. Determine the number of orders per year. (Round your answer to 2 decimal places.)

 

  Number of order per year

 

Problem 13-17

 

A manager just received a new price list from a supplier. It will now cost $1.00 a box for order quantities of 801 or more boxes, $1.10 a box for 200 to 800 boxes, and $1.20 a box for smaller quantities. Ordering cost is $80 per order and carrying costs are $10 per box a year. The firm uses 3,600 boxes a year. The manager has suggested a “round number” order size of 800 boxes. The manager’s rationale is that with a U-shaped cost curve that is fairly flat at its minimum, the difference in total annual cost between 800 and 801 units would be small anyway. What order size would you recommend? (Round intermediate calculations to 2 decimal places and final answer to the nearest whole number.)

 

 

  Recommended order size  

 

Problem 13-18

 

A newspaper publisher uses roughly 860 feet of baling wire each day to secure bundles of newspapers while they are being distributed to carriers. The paper is published Monday through Saturday. Lead time is six workdays. What is the appropriate reorder point quantity, given that the company desires a service level of 95 percent, if that stockout risk for various levels of safety stock is as follows: 1,500 feet, .10; 1,700 feet, .05; 2,100 feet, .02; and 2,400 feet, .01?

 

 

  Appropriate reorder point ft

 

Problem 13-31

 

A drugstore uses fixed-order cycles for many of the items it stocks. The manager wants a service level of .98. The order interval is 12 days, and lead time is 3 days. Average demand for one item is 61 units per day, and the standard deviation of demand is 12 units per day. Given the on-hand inventory at the reorder time for each order cycle shown in the following table.
Use Table .

 

 

Cycle On Hand
1 42
2 13
3 105
 

 

Determine the order quantities for cycles 1, 2, and 3: (Round your answers to the nearest whole number)

 

Cycle           Units
1  
2  
3  
 

 

 

http://www.viddler.com/embed/4d240300#

http://www.viddler.com/embed/df5870c6#

http://www.viddler.com/embed/195ff05f#

http://www.viddler.com/embed/dde2e03b#

 

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

-2-2

 

http://ezto.mhedu

 

http://ezto.mhedu

Do you need a similar assignment written for you from scratch? We have qualified writers to help you. You can rest assured of an A+ quality paper that is plagiarism free. Order now for a FREE first Assignment! Use Discount Code "FREE" for a 100% Discount!

NB: We do not resell papers. Upon ordering, we write an original paper exclusively for you.

Order New Solution